Project: Mulholland Bridge Demolition

Client: Penhall Company

Value: Private

Start Date: 9/2011

Description: Miller Environmental, Inc. was contracted to perform the 24 hour per day demolition of the 85' tall bridge spanning the 405 freeway. This project involved the full closure of the 405 in both directions for about 56 hours. During the project we used two (2) high reach excavators with 100' capabilities. One (1) 100,000 lb. excavator with a Labounty 3000R Shear second member and a 980 size rubber tire loader. Our crews worked two - 12 hour shifts and the schedule was bettered by 15 hours.