Project: BF Goodrich Aerospace Abatement and Demolition.

Client: Port of San Diego

Value: $3,800,000.00

Start Date: 2008

Description: Miller Environmental was contracted to provide the abatement and demolition of approximately 800,000 SF of buildings over the 30 acre former aerospace campus. Miller worked more than 25,000 man hours on this project. This was the largest single abatement and demolition project performed in San Diego during 2008.

The project was completed on time and under budget. The recycling effort generated a rate of 70% over the course of the job which was very high as minimal concrete was removed from the site.